This is the first housing project carried out by the Guernsey Housing Association, its aim being to provide affordable high quality housing for the rental market.
The construction of the 34 one and two bedroom apartments was carried out under an 18 month " design and build " contract, which was completed on time and on budget during the summer of 2004.
Ground conditions dictated the use of piled foundations and ground beams.
Surface water drainage required a difficult 400m connection to be made.
The close proximity of a busy school and small local roads required considerable organisation and sensitivity during construction.
A series of external paved courtyard areas provide " outdoor living ", and the use of natural light within the flats has been maximised.
The building sits on an underground residents car park.
The development features two " turret " apartments, one with a flat roof terrace.
Specific attention was given to details such as brick dentils, render bands and granite.
The Guernsey Housing Association were delighted with the end result and commended all involved.